Work Order SLA: Time Limits and Delay Justifications
Learn what a work order SLA (tazmeen) is, how to set day limits per stage, when to require delay justifications, and how to catch overdue orders early.
Quick answer
A work order SLA, known in Arabic as tazmeen, is the number of days a work order may stay in each stage, such as site survey, permits, execution or quality, before it counts as overdue. The clock starts when the order is relayed into the stage or when the responsible user claims it, depending on the setting. Once the limit passes, a delay justification with evidence explains why.
Key takeaways
- A work order SLA sets a day limit for each stage, not one deadline for the whole order.
- Counting from relay measures waiting plus working time; counting from receipt measures only the time after someone takes the order.
- Base limits on your own completed orders and on published timelines such as permit processing times, then review them regularly.
- A good delay justification names the cause, its date and the party involved, and attaches proof. It documents a delay; it does not excuse it.
- In ELX, each stage has its own limit, overdue orders are flagged in lists and on the dashboard, and a mandatory justification can block relay.
In this article
A utility work order passes through a chain of stages before a contractor can bill for it: site survey (Kashfia), an excavation permit when needed, execution in Projects or Connections, quality, the achievement certificate, drawing and the extract. Every idle day in one stage delays everything after it, including the payment claim.
A work order SLA makes that delay visible: a time limit for each stage, and a written justification when it is missed. Here is how to design one that your teams will actually respect.
What is a work order SLA (tazmeen)?
A work order SLA is the number of days a work order may stay in each stage before it is flagged as overdue. The Arabic term is tazmeen (التزمين). It applies the service level agreement idea to each stage separately, not to the order as a whole.
Instead of asking “when will this order be done?”, you ask “is this stage within its limit?” If not, the next question is “why?”, and the answer is recorded as a delay justification with evidence.
- Stage time limit
- The allowed number of days for one stage of a work order.
- Time limit exceeded
- The order has stayed in the stage past its limit and counts as overdue.
- Delay justification
- A written reason for the overrun, backed by a document or photo.
- Relay
- Moving the order to the next stage once the current stage is complete.
- Receipt
- The moment the responsible user claims the order in a stage.
Why does every stage need a time limit?
A single deadline tells you an order is late, not where it got stuck. Each stage has its own owner: survey, permits, execution crews, quality inspectors, certificate and drawing staff, then finance. With a limit and an owner per stage, a delay becomes a question for a specific person, not a general complaint.
- Ownership: every overdue day belongs to a known stage and team.
- Bottlenecks: overdue orders piling up in one stage point to a staffing gap or a recurring obstacle.
- External timelines: stages that wait on others, such as the municipality for permits, need limits that allow for those outside timelines.
- Cash flow: an order reaches the extract only after the earlier stages close, so a slow quality, certificate or drawing stage holds back payment.
- A defensible record: dated justifications document what happened, for any later review.
Before setting limits, agree on what happens in each stage and who owns it. Our guide to utility work order stages walks through them.
Should the count start at relay or at receipt?
This first decision changes what the number means. Counting from relay starts the clock when the order arrives in a stage, whether or not anyone has picked it up. Counting from receipt starts it when the responsible user claims the order.
It also interacts with the relay mode. With automatic relay, the order goes straight into the next stage’s list for one of its users to claim. With manual relay, it waits in a distribution basket until a dispatcher assigns it. Either way, days can pass before anyone picks it up.
| Criterion | From relay | From receipt |
|---|---|---|
| Clock starts | When the order enters the stage | When a user claims the order |
| Measures | Waiting time plus working time | Working time after receipt only |
| Reveals | Slow dispatching and crowded stage baskets | Slow work by the assigned user |
| Can hide | Whether the dispatcher or the doer caused the delay | Days spent waiting, in a basket or stage list, before anyone claimed the order |
| Best for | Managers tracking the total time an order has been open | Teams that want a fair measure of individual performance |
Neither is right for everyone. If you count from receipt, track the waiting time before receipt as a separate indicator. If you count from relay, ask each justification to say whether the delay came before or after the order was claimed.
How do you set realistic limits per stage?
Realistic limits come from your data, not from wishful targets. Set them too tight and most orders turn red, so people stop reacting. Set them too loose and problems stay hidden until they pile up.
Collect actual durations
From completed orders, find the typical time each stage takes, per work type if you can.
Separate internal from external
Split stages your team controls from those that wait on others, such as permits or power disconnection.
Anchor on published timelines
For official processes, treat the published timeline as the floor and add your preparation time.
Choose counting and relay modes
Decide whether the clock runs from relay or receipt, and whether each stage relays automatically or through a basket.
Pilot, then review
Run the limits for a while, review the overdue share and its reasons, then adjust the limit or fix the cause.
Published timelines that help anchor some stages:
| Stage | What takes the time | External reference |
|---|---|---|
| Permits (new excavation permit) | Documents, submission, fees | The Ministry of Municipalities and Housing lists a processing time of 1–2 days for a new excavation permit, issued once fees are paid. |
| Permits (emergencies) | Starting work, then the formal request | Emergency excavation permit: work may start after preliminary approval; the formal request is due within 24 hours of the notification and is reviewed within 24 hours at most. |
| Projects and Connections | Execution, excavations, material requests | Regulations announced in March 2024 set general excavation licenses at 30 days on highways and 60 days on main, secondary and local roads, so plan excavation to finish within the license period. |
| Extracts | Grouping completed orders, approval | If your contract uses FIDIC 1999 conditions, Sub-Clause 14.7 gives the employer 56 days to pay each Interim Payment Certificate after the Engineer receives the contractor’s Statement and supporting documents. |
| Survey, quality, certificate, drawing | Internal work by your teams | No general published timeline; check your contract terms and your own order history. |
Under FIDIC-based contracts, the payment window opens only once supporting documents arrive, so every day lost before the extract pushes it back. For the claim itself, see our guide to the contractor extract.
Illustrative example
These numbers are for illustration only, not a benchmark. If your records show most surveys close in three days, start near three rather than an ideal one or a comfortable ten. For permits, add the published processing time to the time your team needs to prepare documents and pay fees.
What are delay justifications and which documents support them?
A delay justification is a written explanation, recorded when an order exceeds its stage limit, stating the cause and attaching proof. Write it while the obstacle is fresh, not months later during an extract or penalty review.
| Cause of delay | Suggested evidence |
|---|---|
| Excavation permit not yet issued | Request number and date, plus request status or correspondence |
| Survey or materials do not match | The matching form sent, its date and recipients |
| Waiting for power disconnection | The disconnection request and date, then proof of disconnection |
| Materials missing for execution | The material request and date, with quantities received and still needed |
| Site obstacle | Dated site photos and a report or letter describing it |
| Order returned with quality comments | The failed evaluation items and the execution team’s response |
Before accepting a justification, check it against this list:
- The cause is specific, not a vague phrase such as “site conditions”.
- The date the obstacle began is stated and matches the stage dates.
- The party linked to the obstacle is named.
- A dated document or photo is attached.
- The corrective action is stated, with an expected date.
- It is written by the user responsible for the stage.
A justification documents a delay; it does not excuse it
A delay justification records why a limit was exceeded. It does not guarantee a waived penalty or the employer’s acceptance; that depends on your contract and the assessing party. Its value is a dated record for any review, and a clear view of causes that keep recurring.
How do you catch overdue orders before they pile up?
Without a regular review, an overdue order may surface only when someone complains or a claim is disputed. The fix is a short daily review, not a post-mortem.
- Each morning, review overdue orders stage by stage, oldest first.
- Watch orders nearing their limit; acting early beats justifying later.
- Track how long orders wait in baskets and stage lists before anyone claims them, especially if you count from receipt.
- Compare order ages in time buckets; growth in the oldest buckets is an early warning.
- Group delay reasons weekly. A recurring cause needs a fix, not another justification.
- Check the excavation permit’s expiry against the execution limit.
A dashboard is the natural place for this review. See our work order dashboard guide for the indicators, and excavation permit tracking for permit follow-up.
What mistakes undermine stage time limits?
- One limit for every stage: a survey and an execution stage do not take the same time, so a single limit is unfair to one and too lenient on the other.
- Limits without justifications: if nobody explains an overrun, the red number becomes background noise.
- Justifications without attachments: text alone is hard to verify months later.
- Ignoring waiting time: an order sitting for days in a basket or stage list is already late, even before the receipt clock starts.
- Limits nobody revisits: new crews or a new work mix make old limits unrealistic.
See stage time limits and delay justifications in ELX
We show how each stage gets a limit in days, and how ELX asks for a delay justification with files before a late order moves on.
How does ELX apply stage time limits and delay justifications?
ELX is a bilingual cloud (SaaS) system hosted and operated by Matrix. It runs in the browser, with no servers needed on your side, and carries each work order for electricity-network contractors from registration to archive. Stage time limits are part of its work order management, not a month-end report.
- A limit per stage: in the permissions and settings area, the administrator sets each stage’s allowed days, relay mode (automatic, or manual through a distribution basket), mandatory notes or attachments, and whether an overrun requires a justification.
- Counting mode: the general settings decide whether the clock runs from relay or from receipt.
- Justification before relay: an overdue order with a mandatory justification cannot be relayed until the justification and its supporting files are entered. Users can save it alone, or save and relay together.
- Overdue flags: overdue orders appear in stage lists with a delay-justifications action and are colour-marked in distribution screens with a legend; survey orders can be filtered by status to show only those past their limit.
- Days remaining: stage screens show days remaining or overdue against the order’s expected duration.
- Context for dispatchers: delay justifications are visible on the same distribution screen used to assign the order.
For managers, the dashboard and reports show each stage, from work order to drawing, as within-limit versus late; clicking the late slice lists those orders and who holds each. The daily digest, sent on Telegram and on WhatsApp when enabled, groups order ages into buckets (0–2, 3–7, 8–14 and over 14 days) and shows the load per stage.
For the paper trail, the full work order report shows each stage’s relay and receipt dates, and a manual stage change requires a note, logged with the old value, new value and date.
Good to know
ELX sends work order alerts on Telegram, and on WhatsApp when enabled, when an order enters a new stage and in the daily digest; overdue orders surface in stage lists, distribution screens and the dashboard. Excavation permits are tracked by recording their details; ELX does not connect to Balady.
If your stages work differently, Matrix customizes screens, reports and stages to each contractor’s needs. Request a demo to see how the time-limit and delay-justification settings fit your own stages.
Want to see ELX on your own projects?
Request a demo from our team on WhatsApp and see how work orders, extracts and warehouses run in one system.
Frequently asked questions
What does tazmeen mean for work orders?
Tazmeen is the Arabic term for a work order SLA: the number of days a work order may stay in each stage, such as site survey, permits, execution or quality, before it is flagged as overdue. It shows which stage is holding an order and which team owns it, and an overrun calls for a written delay justification with evidence.
Can the system block relaying an overdue order until a justification is added?
Yes, where the system supports it. In ELX, the administrator can make a delay justification mandatory for any stage they choose. Once an order passes its limit, it cannot be relayed to the next stage until the justification text and supporting files are entered. Users can save the justification on its own and relay later, or save and relay in one step.
Should the time limit start at relay or at receipt?
Counting from relay starts the clock when the order arrives in the stage, so it covers waiting time as well as working time and exposes slow dispatching. Counting from receipt starts when the responsible user claims the order, which is fairer to individuals but can hide days spent waiting in a basket or stage list. If you choose receipt, track that waiting time separately.
How do I find work orders that exceeded their stage limit?
Review overdue orders stage by stage every day instead of waiting for complaints. In ELX, orders past their limit are flagged in stage lists and distribution screens, and the dashboard shows each stage’s within-limit and late orders side by side. Clicking the late slice opens a list of those orders and the user who currently holds each one.
Which documents support a delay justification?
Use evidence that proves both the cause and its date: the permit request number and date for a delayed excavation permit, the matching form sent for a survey or material mismatch, the disconnection request for a wait on power disconnection, and dated site photos for a field obstacle. A justification documents the delay; it does not guarantee a waived penalty.
Sources & references
- MOMAH – Request for Issuance of a New Excavation Permit
- MOMAH – Emergency Excavation Permit
- MOMAH – News: new Excavation Licenses Regulations and license periods
- FIDIC – Contracts FAQ (1999 Construction, Plant, EPCT) — Applies only where the contract uses FIDIC conditions